Gigafactory 3
from Tesla

It was China that attracted the company's attention for a reason. The Celestial Empire remains the second largest market for Tesla lagging behind only the USA. The Chinese government support made it possible to build Gigafactory 3 in record time.

Shanghai, China

It took Tesla only 168 days (or about six months) to go from obtaining construction permits to connecting the brand new factory to grid. The company made great emphasis on process automation: most of the plant area is occupied by hundreds of robots, which are involved in almost all stages of production.

STATE SUPPORT MEASURES:
  • 10% vehicle sale tax is abolished for the factory products;
  • USD 565 m - a working capital loan from the Industrial and Commercial Bank of China;
  • 25% vehicle import tax is abolished for the factory products.
  • It took 1 year to build the factory
  • USD 2 bn.- factory construction cost
  • 250,000 vehicles - annual factory capacity
  • + 98% increase in demand for company products
  • + 65% savings compared to a factory in the USA
  • 2,000 people in factory staff
  • 86.5-ha land plot
  • 17.3-ha building area
2018, May
2018, May
Tesla subsidiary founded in Shanghai.
2018, July
2018, July
Factory construction agreement signed with the regional government of Shanghai.
2018, October
2018, October
Tesla won the tender for long-term land rent.
2019, January
2019, January
Official groundbreaking ceremony of the factory.
2019, August
2019, August
Construction completed and factory equipment started.
2019, December
2019, December
Production cycle start.
2020, January
2020, January
First 15 vehicles delivered to first customers.
2021, January
2021, January
Plan to complete construction and to launch the second production line.